Projects Currently Bidding
Projects Currently Bidding
Following are brief descriptions of projects currently bidding at UCLA, including links to complete advertisements and announcements containing information on where bidding documents can be obtained and the deadline for submitting bids. These advertisements and announcements may be viewed, saved and printed in Adobe Acrobat Portable Document Format (PDF). For more information on saving and printing files, see Help.
Ad for Bid
Ad for PQ Prime
Ad for PQ Sub
Ad for Subs
Announcement to PQ Bidders
| Ad for Bid | |
|---|---|
| Project Name |
BSRB ROOM B-64 DRY HEAT STERILIZER INSTALLATION (RE-BID) (opens in new tab, PDF)
|
| Project Number | 907078.01 |
| Project Description | Subject to conditions prescribed by the University of California, Los Angeles, sealed bids for a lump sum contract from prequalified bidders are invited for the following work:
The Division of Laboratory Animal Medicine (DLAM) at the David Geffen School of Medicine (DGOSM) proposes to replace an obsolete steam autoclave with an electric dry heat sterilizer for mice cages in Room B-64 of the Biomedical Sciences Research Building (BSRB). The total project area is approximately 1,666 asf (1,998 gsf). BSRB is a 134,753 gsf (90,557 asf) six-story building, plus a basement level, constructed in 2007. BSRB houses DLAM’s Breeding Colony Management Program, which maintains approximately 7,800 mice cages. The scope of work includes the removal of the existing decommissioned steam autoclave and associated steam pipes; upgrades to the building’s electrical, mechanical, and plumbing systems; provision of an electric dry heat sterilizer; and seismic anchorage, fire/life safety, and accessibility improvements. The estimated construction cost is $2,180,746. TO VIEW AND DOWNLOAD ALL FURTHER INFORMATION (PREQUALIFICATION DOCUMENTS IF ANY; BIDDING DOCUMENTS; ADDENDA IF ANY; CONFERENCE/JOB WALK SIGN-IN SHEET; PLANHOLDERS LIST; PREQUALIFIED BIDDERS, IF ANY, ETC.), CLICK HERE: UCLA ONLINE PLANROOM |
| Estimated Construction Cost | $2,180,746.00 |
| Project Name |
Wasserman OR Booster Chiller Installation (opens in new tab, PDF)
|
| Project Number | 35399-CP1513 |
| Project Description | Subject to conditions prescribed by the University of California, Los Angeles, sealed bids for a lump sum contract from prequalified bidders are invited for the following work:
The scope of work for this project includes the furnishing and installing of new booster chiller equipment and associated pumps to serve the existing AHU-3 at the Wasserman Building mechanical penthouse. The work also includes replacement of the existing cooling coil and humidifier dispersion tubes serving AHU-3, along with all required mechanical, electrical, controls, support, and testing work needed to place the system into operation. Mechanical scope includes furnishing and installing a new water-cooled chiller, new chilled water pumps, buffer tank, and related piping and accessories required for the new chilled water system. The existing cooling coil and humidifier dispersion tubes serving AHU-3 will be replaced. The project will also include testing and balancing by an independent AABC-certified agent. Electrical scope includes providing a new electrical panel to serve the new equipment as required. The new panel will be fed from an existing switchboard located on the lower level of the building. New electrical conduits and supports will be routed from the lower level up to the penthouse to provide power to the new equipment and associated accessories. Architectural/demo scope includes temporary removal and replacement of existing ceiling tiles and grid as needed to provide new conduits and supports. Existing hard-lid ceiling areas will also be demolished where required to support conduit routing and installation. Since electrical conduits will be routed vertically through the building shaft, the shaft area will be accessed as needed to complete the conduit installation from the lower level to the penthouse. The work area is primarily located on the west side of the roof within the mechanical penthouse, with additional work on the fifth level and lower level as required for conduit routing, electrical connections, and access to existing building infrastructure. Due to the sensitive and occupied nature of the facility, all project work shall be performed during nighttime hours, except for work within the roof penthouse, which may be performed during normal working hours. TO VIEW AND DOWNLOAD ALL FURTHER INFORMATION (PREQUALIFICATION DOCUMENTS IF ANY; BIDDING DOCUMENTS; ADDENDA IF ANY; CONFERENCE/JOB WALK SIGN-IN SHEET; PLANHOLDERS LIST; PREQUALIFIED BIDDERS, IF ANY, ETC.), CLICK HERE: UCLA ONLINE PLANROOM |
| Estimated Construction Cost | $600,000.00 |
| Project Name |
Deferred Maintenance FY2021-22 - NRB (opens in new tab, PDF)
|
| Project Number | 942418.01 |
| Project Description | Subject to conditions prescribed by the University of California, Los Angeles, sealed bids for a lump sum contract from prequalified bidders are invited for the following work:
This project will replace the obsolete Building Automation Controls and bladder-actuated Variable Air Volume (VAV) boxes in the Neuroscience Research Building (NRB), as identified by an Integrated Capital Asset Management Program (ICAMP) facility condition assessment. The replacements would increase overall building efficiency, reduce future maintenance costs, and bring the systems into compliance with current building codes. The NRB is a six-story facility, including a basement, totaling 130,887 gsf (80,259 asf), constructed in 2004. The building houses a vivarium, as well as wet and dry labs designed to accommodate a wide range of research needs for the Department of Neurobiology and the Brain Research Institute, focusing on how the brain develops, functions, and is affected by disease. The proposed scope of work includes renovating the existing lab spaces with updated air valves for air supply and exhaust, re-adjusting deferred maintenance items related to airflow levels, reconnecting the valves to the existing control system, and testing and balancing for the air and water systems. No modifications would be made to the existing life safety, smoke control, or fire alarm sequencing, control devices, or signals. Any additional control architecture and devices added in parallel would support only non-critical equipment and operations. Hazardous materials abatement shall be required in survey identified areas containing lead paint if areas disturbed. The estimated construction cost is $6,105,294. TO VIEW AND DOWNLOAD ALL FURTHER INFORMATION (PREQUALIFICATION DOCUMENTS IF ANY; BIDDING DOCUMENTS; ADDENDA IF ANY; CONFERENCE/JOB WALK SIGN-IN SHEET; PLANHOLDERS LIST; PREQUALIFIED BIDDERS, IF ANY, ETC.), CLICK HERE: UCLA ONLINE PLANROOM |
| Estimated Construction Cost | $6,105,294.00 |
| Project Name |
SMUMC Room 3411 Interventional Radiology Equipment Replacement (opens in new tab, PDF)
|
| Project Number | 944668 |
| Project Description | Subject to conditions prescribed by the University of California, Los Angeles, sealed bids for a lump sum contract are invited for the following work:
This project is proposed by the Radiology Department at UCLA Santa Monica Medical Center. The project would renovate approximately 884 asf (965gsf) in Room 3411 and the adjacent control and equipment rooms. Additionally, a new Interventional Radiology (IR) imaging system will be installed in room 3411 on the third floor of Santa Monica UCLA Medical Center (SMUMC). This scope of work will include interior improvements, structural strengthening, modifications to building mechanical, electrical, and plumbing systems, including nurse call, fire alarm, fire sprinkler and security systems to support the new Interventional Radiology equipment and associated items. Work may also include repairs to building finishes impacted by the work. Equipment will be procured separately. TO VIEW AND DOWNLOAD ALL FURTHER INFORMATION (PREQUALIFICATION DOCUMENTS IF ANY; BIDDING DOCUMENTS; ADDENDA IF ANY; CONFERENCE/JOB WALK SIGN-IN SHEET; PLANHOLDERS LIST; PREQUALIFIED BIDDERS, IF ANY, ETC.), CLICK HERE: UCLA ONLINE PLANROOM |
| Estimated Construction Cost | $2,930,000.00 |
| Project Name |
Gonda Center Deep Energy Project (RE-BID) (opens in new tab, PDF)
|
| Project Number | 943981.01 |
| Project Description | Subject to conditions prescribed by the University of California, Los Angeles, sealed bids for a lump sum contract from prequalified bidders are invited for the following work:
This project will upgrade existing air handling units and lighting systems within the Gonda Center to reduce the building’s annual energy usage by approximately 45 percent. Most energy savings will be achieved by converting laboratory air handling units from constant-volume to variable-airflow systems. Other opportunities for energy efficiency include programming upgrades for system controls and new lighting. The Work shall include several measures referenced as ECMs in the contract documents. Laboratory exhaust valves will be converted from constant volume to variable air volume (VAV). In laboratory spaces, occupancy sensors shall be installed to reduce air changes and exhaust controls would be modified on fume hoods. New system strategies shall reduce equipment use through control of scheduling, temperature, pumps, and start/stop optimization. Lights and lighting control improvements shall include replacing fluorescent lights with LEDs. Related scope shall include patch and paint of walls in areas impacted by the work. In locations where equipment is above the existing ceilings grids, work shall include ceiling removal and re-installation, or replacement, after work is complete. The base bid shall be comprised of the ECMs designated as “BASE LIGHTING,” “BASE HVAC” and “ADD-ALT 4 within the SCOPE MATRIX on drawing M0.2. Additionally, Alternates 1 and 3 of this same matrix may be considered as part of this project. All work shall be performed in a fully operational and restricted building. Night and off-shift work will be required in sensitive areas as identified by University Representative. Contractor shall maintain building security at all times and will be responsible for furnishing access to workers and vendors for deliveries. Contractor shall include an initial air survey of as-built condition for all areas and equipment under the scope of work. TO VIEW AND DOWNLOAD ALL FURTHER INFORMATION (PREQUALIFICATION DOCUMENTS IF ANY; BIDDING DOCUMENTS; ADDENDA IF ANY; CONFERENCE/JOB WALK SIGN-IN SHEET; PLANHOLDERS LIST; PREQUALIFIED BIDDERS, IF ANY, ETC.), CLICK HERE: UCLA ONLINE PLANROOM |
| Estimated Construction Cost | $7,058,000.00 |
| Project Name |
UWVMC 2nd Floor Sterilizer Replacement (opens in new tab, PDF)
|
| Project Number | 40293-CP1576 |
| Project Description | Subject to conditions prescribed by the University of California, Los Angeles, sealed bids for a lump sum contract prequalified bidders are invited for the following work:
Contractor shall replace the 2nd Floor STERRAD 100NX sterilizer equipment. Scope of work includes equipment anchorage and new electrical power & data port junction wall box for sterilizer equipment. The project shall be completed during night work only. The occupied space is a clean/sanitized environment. Work inside this sanitized space will require a temporary construction barrier that meets the highest Infection Prevention Level 5 to mitigate dust. A temporary construction barrier may be constructed using 6-mil plastic or heavier. A temporary Gyp Board barrier is not recommended inside this clean/sanitized SPD area. TO VIEW AND DOWNLOAD ALL FURTHER INFORMATION (PREQUALIFICATION DOCUMENTS IF ANY; BIDDING DOCUMENTS; ADDENDA IF ANY; CONFERENCE/JOB WALK SIGN-IN SHEET; PLANHOLDERS LIST; PREQUALIFIED BIDDERS, IF ANY, ETC.), CLICK HERE: UCLA ONLINE PLANROOM |
| Estimated Construction Cost | $386,000.00 |
| Project Name |
Building Automation Unit Price Job Order - Facilities Management 2026 (opens in new tab, PDF)
|
| Project Number | 8660900 |
| Project Description | Subject to conditions prescribed by the University of California, Los Angeles, sealed bids for a Unit Price Job Order ("UPJO") contract are invited for the following work:
The University seeks to hire a contractor to perform building automation construction work on an "as needed" basis that will be delivered by Unit Price Job Order (UPJO), and occur on the UCLA Westwood campus as well as off-campus facilities owned by the University. As described in more detail in the Bidding Documents, work under the UPJO will be limited to the following: Building automation construction work related to Minor Capital Improvement Projects delegated to Facilities Management, as well as work delegated to Facilities Management which includes repairs of, or alterations to, buildings, structures, or facilities to continue their usability at the designed level of service. Each Job Order shall have at least 51% of the work within the advertised license classification specified herein. Work outside said license classification may be self-performed by Contractor when said work is considered incidental and supplemental to the performance of the work in the craft for which the specialty contractor is licensed and is essential to the accomplishment of the work in which the contractor is classified. In such cases, the value of said incidental and supplemental work shall not exceed 5% of the Job Order Sum. If the work outside the Contractor’s license classification exceeds 5% of the Job Order Sum, then Contractor must either hold the appropriate additional specialty license classification or subcontract the work to an appropriately licensed subcontractor. Refer to Exhibit 21 of the bidding documents for work excluded from this UPJO. The total combined cost for all Job Orders issued will not exceed the Maximum Contract Value of $3,000,000.00 during the 1-year Base Term and $3,000,000.00 during each 1-year Option Term, if exercised by University. When the work of a job consists only of the trade of this UPJO, the cost of any individual Job Order Authorization will be from $50,000.00 to $1,800,000.00. When the work of a job consists of multiple trades, the cost of any individual Job Order Authorization for this UPJO will be from $1,000.00 to $1,800,000.00. TO VIEW AND DOWNLOAD ALL FURTHER INFORMATION (PREQUALIFICATION DOCUMENTS IF ANY; BIDDING DOCUMENTS; ADDENDA IF ANY; CONFERENCE/JOB WALK SIGN-IN SHEET; PLANHOLDERS LIST; PREQUALIFIED BIDDERS, IF ANY, ETC.), CLICK HERE: UCLA ONLINE PLANROOM |
| Project Name |
Telecomm Structured Cabling JOC - Medical & Off-Campus 2026 (opens in new tab, PDF)
|
| Project Number | ITSJOC-2026-3 |
| Project Description | Subject to conditions prescribed by the University of California, Los Angeles, sealed bids for a Job Order Contract are invited for the following work:
University is seeking to hire a contract to self-perform without subcontractors, telecommunications structured cabling work that will be delivered by Job Order Contracting (JOC). As directed in more details in the Bidding Documents, Work under the JOC will be limited to the following: 1. Intra-building telecommunications structured cabling construction involving low voltage systems trade work where the value of each job performed is between $1.00 and $350,000.00, and where work is performed only in the following locations: a. On-Campus: Ronald Reagan UCLA Medical Center, 200 Medical Plaza, and 300 Medical Plaza; and b. Off-Campus: All University-owned off-campus buildings (except as excluded below) including the Santa Monica UCLA Medical Center & Orthopedic Hospital. For all work on this Contract to be performed inside Health Care Facilities, Contract shall comply with the requirements set forth by the California Department of Public Health for Health Care Facilities. See Section 01 35 13 for further information. The following scope is excluded from this contract: 1. The UCLA Wilshire Center building located at 10920 Wilshire Boulevard, Los Angeles, CA 90095. 2. The UCLA Westwood Center building located at 924 & 936 Westwood Boulevard, Los Angeles, CA 90024. 3. The UCLA Hammer Museum and tower building located at 10889 Wilshire Boulevard, Los Angeles, CA 90024. 4. The UCLA Lake Arrowhead Conference Center in Lake Arrowhead, CA. 5. All buildings purchased by University after the date that this Project's bidding documents become available to bidders. 6. Structured cabling maintenance work, and provisioning of copper and/or fiber patch cables/cords. 7. Inter-Building structured cabling construction involving low voltage systems trade work. The Job Order Contract will have a Maximum Contract Value of $1,000,000.00 for the 1-year Base Term, and $1,000,000 during each 1-year Option Term, if exercised by the University. The Job Order Contract will have a Maximum Contract Value of $1,000,000.00 for the 1-year Base Term, and $1,000,000.00 during each 1-year Option Term, if exercised by University. TO VIEW AND DOWNLOAD ALL FURTHER INFORMATION (PREQUALIFICATION DOCUMENTS; ADDENDA, IF ANY; PQ CONFERENCE SIGN-IN SHEET; ETC.), CLICK HERE: UCLA ONLINE PLANROOM |
| Ad for PQ Prime | |
| Project Name |
MP200 Suite B114 Nuc Med Equipment Installation (PREQUALIFICATIONS) (RE-SOLICITATION) (opens in new tab, PDF)
|
| Project Number | 907558.01 |
| Project Description | Subject to conditions prescribed by the University of California, Los Angeles, responses to the University's prequalification documents for a CM at Risk contract are sought from prospective prime contractor bidders (hereafter “bidders”) for the following project:
The proposed project will renovate the existing Nuclear Medicine Clinic located in the Peter Morton Medical Building at 200 Medical Plaza. The goal of Phase I for this project is to install new SPECT/CT systems and a new Biograph Vision Quadra PET/CT system within the existing Nuclear Medicine doctors’ office area. The project scope also includes upgrades and modifications to the existing HVAC. TO VIEW AND DOWNLOAD ALL FURTHER INFORMATION (BIDDING DOCUMENTS; ADDENDA IF ANY; CONFERENCE/JOB WALK SIGN-IN SHEET; PLANHOLDERS LIST; PREQUALIFIED BIDDERS, ETC.), CLICK HERE: UCLA ONLINE PLANROOM |
| Estimated Construction Cost | $8,323,000.00 |
| Project Name |
Cogeneration Plant New Electric Chiller (PREQUALIFICATION) (opens in new tab, PDF)
|
| Project Number | 943904.01 |
| Project Description | Subject to conditions prescribed by the University of California, Los Angeles, responses to the University's prequalification documents for a CM at Risk contract are sought from prospective prime contractor bidders (hereafter “bidders”) for the following project:
The Cogeneration Plant is an approximately 189,110 gross-square-foot facility that provides electricity, steam, and chilled water to the campus and the Ronald Reagan UCLA Medical Center (RRUMC). The plant operates based on a natural gas-fired cogeneration process and includes a mix of steam-driven, absorption, and electric chillers. As campus growth and peak cooling demand have increased, the existing chiller system is approaching its reliable operating limit, with limited capacity margin to accommodate peak conditions or unanticipated equipment outages. Additionally, portions of the steam-driven chiller fleet are aging and nearing the end of their service life, increasing the risk of reduced availability and operational flexibility. The proposed project is driven by the need to restore system reliability, maintain critical redundancy, and support continued campus expansion and mission-critical operations. It also advances UCLA’s broader strategic transition to electrified heating and cooling systems, thereby reducing reliance on fossil-fuel-based infrastructure and associated greenhouse gas emissions, and supporting compliance with UC sustainability and decarbonization policy objectives. The project would install a new high-efficiency electric centrifugal chiller, along with an associated pumping system, cooling tower, and electrical infrastructure, within the existing Cogeneration Plant footprint. The design would leverage original plant provisions for future expansion, including available space, spare system tie-ins, and existing infrastructure capacity, minimizing modifications and construction risk. The project would include installation of major mechanical and electrical equipment, system tie-ins, controls integration with the plant’s distributed control system, and commissioning to ensure reliable, efficient operation. The addition of the new chiller would require integration with the plant’s existing primary and secondary chilled water system and circulating water system, including the installation of new primary and secondary chilled water pumps, modifications to piping systems, and coordination with existing cooling tower operations. To support the additional heat rejection load, a new multi-cell cooling tower would be installed on an elevated structural steel platform above the current ammonia containment area, keeping all new cooling infrastructure within the cogeneration facility while avoiding interference with existing equipment. The project would also include upgrades and integration within the plant’s electrical distribution system to serve the new equipment. The proposed configuration would use existing medium-voltage infrastructure, with a step-down transformer and variable-frequency drive provided with the new chiller to improve efficiency and reduce electrical footprint and cost. Additional electrical work would support new pumps, cooling tower fans, and control systems while maintaining system redundancy and operational flexibility. Existing steam-driven chiller equipment nearing the end of its service life would be gradually decommissioned as new electric chiller capacity is placed in service. TO VIEW AND DOWNLOAD ALL FURTHER INFORMATION (PREQUALIFICATION DOCUMENTS; ADDENDA, IF ANY; PQ CONFERENCE SIGN-IN SHEET; ETC.), CLICK HERE: UCLA ONLINE PLANROOM |
| Estimated Construction Cost | $29,175,806.00 |
| Project Name |
Gayley Center Real Time Safety Center (PREQUALIFICATION) (opens in new tab, PDF)
|
| Project Number | 940042.01 |
| Project Description | Subject to conditions prescribed by the University of California, Los Angeles, responses to the University's prequalification documents for a lump sum contract are sought from prospective prime contractor bidders (hereafter “bidders”) for the following project:
The Office of Campus and Community Safety (OCCS) proposes renovating approximately 11,985 gsf (10,210 asf) of vacant office space previously occupied by UCLA Extension on Level 2 of the Gayley Center to create a Real Time Safety Center (RTSC) to support critical safety and security operations for the UCLA campus. The RTSC will serve as the venue command post for the 2028 Summer Olympics and Paralympics (LA28) when UCLA will host the Olympic and Paralympic Villages. The Gayley Center is a 168,715 gsf (71,259 asf) three-story building with two underground parking levels constructed in 1980. The project would provide two open office areas, two breakout rooms, two conference rooms, 19 private offices, a technology room for critical server equipment, a reception area, and two storage rooms. The overall RTSC area would total approximately 13,300 gsf (10,890 asf). The proposed scope of work includes interior demolition; modifications to interior walls and ceilings; finish upgrades for floors, walls, and ceilings; installation of data conduits and cabling; provisions for power requirements; dedicated server racks; installation of dedicated mechanical units on the roof; mechanical piping modifications on Level 3; an Automatic Transfer Switch (ATS) on Level P1; and electrical connections for a future temporary generator on Level 1. The project will include modifications to the fire alarm, fire sprinkler, building automation system, and mechanical and electrical systems. Construction will be coordinated with the building occupants to minimize noise and other disturbances. TO VIEW AND DOWNLOAD ALL FURTHER INFORMATION (PREQUALIFICATION DOCUMENTS; ADDENDA, IF ANY; PQ CONFERENCE SIGN-IN SHEET; ETC.), CLICK HERE: UCLA ONLINE PLANROOM |
| Estimated Construction Cost | $4,237,000.00 |
| Ad for PQ Sub | |
| Project Name |
5210 Pacific Concourse Dr. Tenant Improvements (BP 20 - Doors, Frames, and Hardware) PREQUALIFICATION (opens in new tab, PDF)
|
| Project Number | 906021.01 |
| Project Description | Clark Construction Group - California LP, the CM at Risk Contractor on this UCLA project is currently seeking prequalification submittals from Doors, Frames, and Hardware subcontractor bidders. Refer to the attached PDF Advertisement and follow instructions therein. |
| Estimated Construction Cost | $3,625,000.00 |
| Ad for Subs | |
| Project Name |
Acosta Operations Center (BP 04 - Interior Glazing) RE-BID (opens in new tab, PDF)
|
| Project Number | 942403.01 |
| Project Description | Suffolk Construction Company., Inc. dba Suffolk-Roel, the CM at Risk Contractor on this UCLA project is currently seeking Bids from Interior Glazing subcontractor bidders. Refer to the attached PDF Advertisement and follow the instructions therein. |
| Estimated Construction Cost | $45,000.00 |
| Project Name |
Acosta Operations Center (BP 13 - Signage) RE-BID (opens in new tab, PDF)
|
| Project Number | 942403.01 |
| Project Description | Suffolk Construction Company., Inc. dba Suffolk-Roel, the CM at Risk Contractor on this UCLA project is currently seeking Bids from Signage subcontractor bidders. Refer to the attached PDF Advertisement and follow the instructions therein. |
| Estimated Construction Cost | $34,600.00 |
| Project Name |
RRUMC 4TH Floor Patient Care Reconfiguration (BP 11 - Demolition, Concrete, Framing and Drywall) (opens in new tab, PDF)
|
| Project Number | 907518.01 |
| Project Description | Subject to conditions prescribed by the University of California, Los Angeles, sealed bids for a lump sum contract are invited from prequalified Demolition, Concrete, Framing and Drywall subcontractors for the following work:
Complete Selective Demolition as shown on the plans and specifications. Furnish and install concrete metal stud framing and finished level 4 drywall at the RRUMC 4th floor project site, floor area 67,464 SQ FT, per specification sections: Subcontractor to perform selective demolition, chipping/sloping and concrete repair as shown on the project plans and described in the bid package scope sheets. This work primarily takes place on the 4th level of the UCLA RRUMC, though there are selective areas on floors 3 and 5 and on the outdoor decks and along Charles Young Drive. Furnish and install concrete, drywall package complete (metal stud framing, insulation, and finished level 4 drywall) plywood for exterior deck protection, as shown on the project plans and described in the bid package scope sheets. This work primarily takes place on the 4th level of the UCLA RRUMC, though there are selective areas on floors 3 and 5 and on the outdoor decks and along Charles Young Drive. Section 024120 - Selective Demolition Section 033000 - Cast-In-Place Concrete Section 006100 – Rough Carpentry Section 072100 – Thermal Insulation Section 078443 – Fire Resistant Joint Systems Section 081113 – Hollow Metal Frames (as applies to installation) Section 083100 – Access Doors and Panels (as applies to installation) Section 09 22 00 - Non-Structural Metal Framing Section 09 27 13 - Glass-Fiber-Reinforced Gypsum (GFRG) Section 09 29 00 - Gypsum Board TO VIEW AND DOWNLOAD ALL FURTHER INFORMATION (BIDDING DOCUMENTS; ADDENDA IF ANY; CONFERENCE/JOB WALK SIGN-IN SHEET; PLANHOLDERS LIST; PREQUALIFIED BIDDERS LIST, ETC.), CLICK HERE: UCLA ONLINE PLANROOM |
| Estimated Construction Cost | $9,775,000.00 |
| Project Name |
RRUMC 4th Floor Patient Care Reconfiguration (BP 5 - Casework / Millwork) (opens in new tab, PDF)
|
| Project Number | 907518.01 |
| Project Description | DPR Construction, A General Partnership, the CM at Risk Contractor on this UCLA project is currently seeking Bids from prequalified Casework / Millwork subcontractor bidders. Refer to the attached PDF Advertisement and follow the instructions therein. |
| Estimated Construction Cost | $5,560,000.00 |
| Project Name |
RRUMC 4th Floor Patient Care Reconfiguration (BP 12 - Tile & Associated Waterproofing) (opens in new tab, PDF)
|
| Project Number | 907518.01 |
| Project Description | DPR Construction, A General Partnership, the CM at Risk Contractor on this UCLA project is currently seeking Bids from prequalified Tile & Associated Waterproofing subcontractor bidders. Refer to the attached PDF Advertisement and follow the instructions therein. |
| Estimated Construction Cost | $1,540,000.00 |
| Project Name |
RRUMC 4th Floor Patient Care Reconfiguration (BP 19 - Window Treatment/ Overhead Curtain) (opens in new tab, PDF)
|
| Project Number | 907518.01 |
| Project Description | DPR Construction, A General Partnership, the CM at Risk Contractor on this UCLA project is currently seeking Bids from prequalified Window Treatment/ Overhead Curtain bidders. Refer to the attached PDF Advertisement and follow the instructions therein. |
| Estimated Construction Cost | $290,000.00 |
| Project Name |
RRUMC 4th Floor Patient Care Reconfiguration (BP 22 - D/B Fire Protection) (opens in new tab, PDF)
|
| Project Number | 907518.01 |
| Project Description | DPR Construction, A General Partnership, the CM at Risk Contractor on this UCLA project is currently seeking Bids from prequalified D/B Fire Protection subcontractor bidders. Refer to the attached PDF Advertisement and follow the instructions therein. |
| Estimated Construction Cost | $965,000.00 |
| Project Name |
RRUMC 4th Floor Patient Care Reconfiguration (BP 25 - Electrical) (opens in new tab, PDF)
|
| Project Number | 907518.01 |
| Project Description | DPR Construction, A General Partnership, the CM at Risk Contractor on this UCLA project is currently seeking Bids from prequalified Electrical subcontractor bidders. Refer to the attached PDF Advertisement and follow the instructions therein. |
| Estimated Construction Cost | $20,000,000.00 |
| Project Name |
RRUMC 4th Floor Patient Care Reconfiguration (BP 9 - Doors/ Frames/ Hardware) (opens in new tab, PDF)
|
| Project Number | 907518.01 |
| Project Description | DPR Construction, A General Partnership, the CM at Risk Contractor on this UCLA project is currently seeking Bids from prequalified Doors/ Frames/ Hardware subcontractor bidders. Refer to the attached PDF Advertisement and follow the instructions therein. |
| Estimated Construction Cost | $2,480,000.00 |
| Project Name |
RRUMC 4th Floor Patient Care Reconfiguration (BP 13 - Acoustical Ceiling) (opens in new tab, PDF)
|
| Project Number | 907518.01 |
| Project Description | DPR Construction, A General Partnership, the CM at Risk Contractor on this UCLA project is currently seeking Bids from prequalified Acoustical Ceiling subcontractor bidders. Refer to the attached PDF Advertisement and follow the instructions therein. |
| Estimated Construction Cost | $1,400,000.00 |
| Project Name |
RRUMC 4th Floor Patient Care Reconfiguration (BP 17a - Resinous Coating) (opens in new tab, PDF)
|
| Project Number | 907518.01 |
| Project Description | DPR Construction, A General Partnership, the CM at Risk Contractor on this UCLA project is currently seeking Bids from prequalified Resinous Coating subcontractor bidders. Refer to the attached PDF Advertisement and follow the instructions therein. |
| Estimated Construction Cost | $830,000.00 |
| Project Name |
RRUMC 4th Floor Patient Care Reconfiguration (BP 20 - Interior Signage) (opens in new tab, PDF)
|
| Project Number | 907518.01 |
| Project Description | DPR Construction, A General Partnership, the CM at Risk Contractor on this UCLA project is currently seeking Bids from prequalified Interior Signage subcontractor bidders. Refer to the attached PDF Advertisement and follow the instructions therein. |
| Estimated Construction Cost | $250,000.00 |
| Project Name |
RRUMC 4th Floor Patient Care Reconfiguration (BP 23 - Plumbing) (opens in new tab, PDF)
|
| Project Number | 907518.01 |
| Project Description | DPR Construction, A General Partnership, the CM at Risk Contractor on this UCLA project is currently seeking Bids from prequalified Plumbing subcontractor bidders. Refer to the attached PDF Advertisement and follow the instructions therein. |
| Estimated Construction Cost | $11,350,000.00 |
| Project Name |
RRUMC 4th Floor Patient Care Reconfiguration (BP 18b - Wall Protection) (opens in new tab, PDF)
|
| Project Number | 907518.01 |
| Project Description | DPR Construction, A General Partnership, the CM at Risk Contractor on this UCLA project is currently seeking Bids from prequalified Wall Protection subcontractor bidders. Refer to the attached PDF Advertisement and follow the instructions therein. |
| Estimated Construction Cost | $4,200,000.00 |
| Project Name |
RRUMC 4th Floor Patient Care Reconfiguration (BP 10 - Glass & Glazing) (opens in new tab, PDF)
|
| Project Number | 907518.01 |
| Project Description | DPR Construction, A General Partnership, the CM at Risk Contractor on this UCLA project is currently seeking Bids from prequalified Glass & Glazing subcontractor bidders. Refer to the attached PDF Advertisement and follow the instructions therein. |
| Estimated Construction Cost | $975,000.00 |
| Project Name |
RRUMC 4th Floor Patient Care Reconfiguration (BP 14 - Resilient Flooring) (opens in new tab, PDF)
|
| Project Number | 907518.01 |
| Project Description | DPR Construction, A General Partnership, the CM at Risk Contractor on this UCLA project is currently seeking Bids from prequalified Resilient Flooring subcontractor bidders. Refer to the attached PDF Advertisement and follow the instructions therein. |
| Estimated Construction Cost | $2,100,002.00 |
| Project Name |
RRUMC 4th Floor Patient Care Reconfiguration (BP 18a - Specialties) (opens in new tab, PDF)
|
| Project Number | 907518.01 |
| Project Description | DPR Construction, A General Partnership, the CM at Risk Contractor on this UCLA project is currently seeking Bids from prequalified Specialties subcontractor bidders. Refer to the attached PDF Advertisement and follow the instructions therein. |
| Estimated Construction Cost | $1,750,000.00 |
| Project Name |
RRUMC 4th Floor Patient Care Reconfiguration (BP 21 - Install Owner Furnished Equipment) (opens in new tab, PDF)
|
| Project Number | 907518.01 |
| Project Description | DPR Construction, A General Partnership, the CM at Risk Contractor on this UCLA project is currently seeking Bids from prequalified Install Owner Furnished Equipment subcontractor bidders. Refer to the attached PDF Advertisement and follow the instructions therein. |
| Estimated Construction Cost | $735,000.00 |
| Project Name |
RRUMC 4th Floor Patient Care Reconfiguration (BP 24 - HVAC) (opens in new tab, PDF)
|
| Project Number | 907518.01 |
| Project Description | DPR Construction, A General Partnership, the CM at Risk Contractor on this UCLA project is currently seeking Bids from prequalified HVAC subcontractor bidders. Refer to the attached PDF Advertisement and follow the instructions therein. |
| Estimated Construction Cost | $10,450,000.00 |
| Announcement to PQ Bidders | |
| Project Name |
DM FY 21-22 CHS A4-141 AHU-17 & CHS A2-156 AHU-20 Replacement (RE-SOLICIT) (opens in new tab, PDF)
|
| Project Number | 6742018 & 6742020 |
| Project Description | The University has completed the prequalification process for bidders. |
| Project Name |
MRL Deep Energy Efficiency Project (opens in new tab, PDF)
|
| Project Number | 943984.01 |
| Project Description | The University has completed the prequalification process for this project. |
| Estimated Construction Cost | $2,823,000.00 |
| Project Name |
School of Dentistry A0-121 & A2-122 Remodel (opens in new tab, PDF)
|
| Project Number | 944674.01 |
| Project Description | The University has completed the prequalification process for this project. |
| Estimated Construction Cost | $2,467,000.00 |
| Project Name |
Cogeneration Plant Cooling Tower Basin Waterproofing Repair (PREQUALIFICATION RESOLICITATION) (opens in new tab, PDF)
|
| Project Number | 906011.01 |
| Project Description | The University has completed the prequalification process for bidders. |
| Estimated Construction Cost | $2,800,000.00 |
| Project Name |
UCLA Research Park East Core and Shell Improvements (opens in new tab, PDF)
|
| Project Number | 940041.01 |
| Project Description | The University has completed the prequalification process for this project. |
| Estimated Construction Cost Range | Up to $310,000,000 |
| Project Name |
Young Hall - DM East Roof Repair (opens in new tab, PDF)
|
| Project Number | 942411.03 |
| Project Description | The University has completed the prequalification process for this project. |
| Estimated Construction Cost | $1,300,000.00 |
| Project Name |
901 Levering Student Housing (BP09 - Cast in Place Concrete, Grind and Polish Concrete) (opens in new tab, PDF)
|
| Project Number | 946289-01 |
| Project Description | The University has completed the prequalification process for this project. |