Project Archive
Includes selected Major Capital Improvement projects recently completed.
| Project Name | Phase | Construction Start | Construction End | Total Project Cost |
|---|---|---|---|---|
| PS-18 Structural Repair | Construction | Apr 2025 |
Mar 2026 |
$0 |
|
|
||||
| Mid-Wilshire Parking Structure Seismic Improvements | Closed | Oct 2024 |
Nov 2025 |
$10,000,000 |
|
|
||||
| MP100 Suite 700 Clinic Renovation | Closed | Feb 2020 |
Feb 2024 |
$13,625,000 |
|
|
||||
| Powell Library Seismic Improvements Phase 1 | Post Construction | Sep 2022 |
Dec 2025 |
$17,000,000 |
|
|
||||
| Nimoy Theater Renovation | Post Construction | Oct 2021 |
Mar 2024 |
$18,300,000 |
|
|
||||
| Rosenfeld Hall Expansion and Renovation | Post Construction | Jan 2021 |
Sep 2023 |
$24,000,000 |
|
|
||||
| Public Affairs Building Seismic Improvements | Post Construction | Feb 2021 |
May 2023 |
$28,548,000 |
|
|
||||
| CHS B-Level GMP Facility | Post Construction | Sep 2021 |
Oct 2024 |
$28,650,000 |
|
|
||||
| CHS South Tower Post-Occupancy Improvements (Floors 2-7) Phase 2 Labs | Post Construction | Jul 2019 |
Feb 2021 |
$33,494,000 |
|
|
||||
| LaKretz Botany Building Renovation | Post Construction | Feb 2019 |
May 2022 |
$36,350,000 |
|
|
||||
| CHS Emergency Power Upgrade | Closed | Apr 2023 |
Dec 2025 |
$39,795,000 |
|
|
||||
| Cogeneration Plant Equipment Replacement | Closed | Jun 2023 |
Mar 2026 |
$82,500,000 |
|
|
||||
| Gayley Heights | Closed | Sep 2018 |
Oct 2024 |
$183,068,000 |
|
|
||||
| Olympic and Centennial Hall | Post Construction | Dec 2018 |
Nov 2021 |
$222,645,000 |
|
|
||||
| Southwest Campus Apartments | Post Construction | Jun 2018 |
Jul 2022 |
$348,000,000 |
|
|
||||