Project Name Phase Construction Start Construction End Total Project Cost
Southwest Campus Apartments Construction Jun 2018 Jul 2022
$383,290,000
Lot 15 Residence Hall Post Construction May 2018 Nov 2021
$223,042,000
10995 Le Conte Apartments Post Construction Mar 2018 Sep 2022
$184,500,000
LaKretz Botany Building Renovation Post Construction Feb 2019 May 2022
$36,350,000
CHS South Tower Post-Occupancy Improvements (Floors 2-7) Phase 2 Labs Post Construction Jul 2019 Feb 2021
$33,600,000
Public Affairs Building Seismic Improvements Construction Feb 2021 May 2023
$28,800,000
Tiverton House HVAC Replacement Construction Dec 2017 Oct 2022
$8,937,000