| Project Name | Phase | Construction Start | Construction End | Total Project Cost | 
                
                    
                        | 5210 Pacific Concourse Dr. Tenant Improvements | Design (P) | Apr 2026 | Jan 2028 
 | $6,500,000 | 
                    
                        | 
                             | 
                    
                        | 901 Levering Student Housing | Design (P) | Dec 2026 | Oct 2030 
 | $8,752,000 | 
                    
                        | 
                             | 
                    
                        | Lake Arrowhead Conference Center Willow Creek Staff Housing | Construction | Dec 2024 | May 2026 
 | $11,965,000 | 
                    
                        | 
                             | 
                    
                        | Mid-Wilshire Parking Structure Seismic Improvements | Construction | May 2024 | Jul 2026 
 | $15,000,000 | 
                    
                        | 
                             | 
                    
                        | MP200 2nd Floor Oncology Improvements | Design | Sep 2025 | Feb 2027 
 | $16,000,000 | 
                    
                        | 
                             | 
                    
                        | Acosta Operations Center | Design | Aug 2026 | Sep 2027 
 | $16,543,000 | 
                    
                        | 
                             | 
                    
                        | UCLA Research Park East Core and Shell Improvements | Design (P) | Feb 2026 | Oct 2028 
 | $19,600,000 | 
                    
                        | 
                             | 
                    
                        | MP200 Emergency Power Equipment Replacement | Design | Jun 2026 | Oct 2027 
 | $20,000,000 | 
                    
                        | 
                             | 
                    
                        | RRUMC Nurse Call Replacement | Design | Sep 2026 | Feb 2030 
 | $21,700,000 | 
                    
                        | 
                             | 
                    
                        | Sunset Canyon Recreation Replacement Building | Design | Jun 2025 | Dec 2026 
 | $38,600,000 | 
                    
                        | 
                             | 
                    
                        | CHS Emergency Power Upgrade | Construction | Apr 2023 | Jan 2025 
 | $39,795,000 | 
                    
                        | 
                             | 
                    
                        | Wooden Center Seismic and Program Improvements | Construction | Jan 2027 | Oct 2026 
 | $47,900,000 | 
                    
                        | 
                             | 
                    
                        | Mid-Wilshire Medical Office Building Seismic and Program Improvements | Construction | Apr 2024 | Jun 2025 
 | $52,000,000 | 
                    
                        | 
                             | 
                    
                        | Cogeneration Plant Equipment Replacement |  | Jun 2023 | Jul 2024 
 | $82,500,000 | 
                    
                        | 
                             | 
                    
                        | Gayley Towers Redevelopment | Construction | Nov 2024 | Sep 2026 
 | $108,000,000 | 
                    
                        | 
                             | 
                    
                        | RRUMC 4th Floor Patient Care Reconfiguration | Design | Mar 2026 | Oct 2027 
 | $169,000,000 | 
                    
                        | 
                             | 
                    
                        | Neuropsychiatric Replacement Hospital | Construction | Apr 2022 | May 2026 
 | $352,000,000 | 
                    
                        | 
                             |